[IMP] project_long_term: Add start date and end date in tasks detail view
authorSbh (OpenERP) <sbh@tinyerp.com>
Tue, 4 Jan 2011 06:36:59 +0000 (12:06 +0530)
committerSbh (OpenERP) <sbh@tinyerp.com>
Tue, 4 Jan 2011 06:36:59 +0000 (12:06 +0530)
bzr revid: sbh@tinyerp.com-20110104063659-rhwstzc0tch71dsq

addons/project_long_term/project_long_term_view.xml

index 61e0a7d..ff4cfd8 100644 (file)
                                     <field name="sequence"/>
                                     <field name="name"/>
                                     <field name="user_id"/>
+                                    <field name="date_start"/>
+                                    <field name="date_end" />
                                     <field name="planned_hours" widget="float_time"/>
                                     <field name="project_id" invisible="1"/>
                                     <field name="total_hours" sum='Total Hours'/>
                                             <group colspan="2" col="2">
                                                   <separator string="Dates" colspan="2"/>
                                                   <field name="date_start"/>
+                                                  <field name="date_end" />
                                                   <field name="date_deadline"/>
                                             </group>
                                             <group colspan="2" col="2">